A Biobjective Optimization Model for Deadline Satisfaction in Line-of-Balance Scheduling with Work Interruptions Consideration
Table 1
Tabular presentation of project data.
| Act | Description | Required man-hours to finish a unit | Number of workers in a crew | Daily working hours | Unit duration (days) |
| A | Mobilization | 192 | 4 | 8 | 6 | B | Surveying | 64 | 2 | 8 | 4 | C | Access road construction | 576 | 6 | 8 | 12 | D | Clearing grubbing | 576 | 8 | 8 | 9 | E | Earthmoving | 1040 | 10 | 8 | 13 | F | Ditch excavation | 400 | 5 | 8 | 10 | G | Culvert installation | 80 | 5 | 8 | 2 | H | Peat excavation and swamp backfill | 192 | 6 | 8 | 4 | I | Embankment | 432 | 6 | 8 | 9 | J | Utility work | 160 | 4 | 8 | 5 | K | Fine grading | 256 | 4 | 8 | 8 | L | Granular base (bulk) | 336 | 6 | 8 | 7 | M | Barrier walls | 576 | 8 | 8 | 9 | N | Granular base (fine) | 384 | 6 | 8 | 8 | O | Signage (foundations) | 1600 | 10 | 8 | 20 | P | Paving (base) | 336 | 6 | 8 | 7 | Q | Signage (installation) | 288 | 4 | 8 | 9 | R | High mast lighting | 224 | 4 | 8 | 7 | S | Paving (wearing course) | 288 | 6 | 8 | 6 | T | Shoulder granular | 320 | 5 | 8 | 8 | U | Lane marking | 16 | 2 | 8 | 1 | V | Landscaping | 72 | 3 | 8 | 3 | W | Checkout and acceptance | 80 | 2 | 8 | 5 | X | Demobilization | 160 | 5 | 8 | 4 |
|
|