A Biobjective Optimization Model for Deadline Satisfaction in Line-of-Balance Scheduling with Work Interruptions Consideration

Table 1

Tabular presentation of project data.

ActDescriptionRequired man-hours to finish a unitNumber of workers in a crewDaily working hoursUnit duration (days)

AMobilization192486
BSurveying64284
CAccess road construction5766812
DClearing grubbing576889
EEarthmoving104010813
FDitch excavation4005810
GCulvert installation80582
HPeat excavation and swamp backfill192684
IEmbankment432689
JUtility work160485
KFine grading256488
LGranular base (bulk)336687
MBarrier walls576889
NGranular base (fine)384688
OSignage (foundations)160010820
PPaving (base)336687
QSignage (installation)288489
RHigh mast lighting224487
SPaving (wearing course)288686
TShoulder granular320588
ULane marking16281
VLandscaping72383
WCheckout and acceptance80285
XDemobilization160584