Research Article

The Application of Fuzzy VIKOR for the Design Scheme Selection in Lean Management

Table 2

Lean management design schemes.

SchemesContents Costs(¥)Objectives

MBO400000MBO 100% done
MBO, PCM550000MBO 100% done; profits improve by 30%
MBO, CM500000MBO 100% done; costs reduce by 10%
MBO, CM, TEB600000MBO 100% done; costs reduce by 10%; TEB 100% done.
MBO, PCM, CM, TEB680000MBO 100% done; profits improve by 30%; costs reduce by 10%; TEB 100% done.