Research Article

Critical Chain Design Structure Matrix Method for Construction Project Scheduling under Rework Scenarios

Table 2

Activity parameters in the case project.

IDActivityLearning curveDuration (day)
MinLikelyMax

APerform prelim. mkt analysis0.55815

BEvaluate marketability options0.65815

CEngage feasibility consultants0.3347

DEvaluate planning & zoning process0.5101320

EPerform massing study0.6202435

FDevelop conceptual design0.8303550

GIdentify external stakeholders0.45815

HIdentify permits & approvals0.7101320

IComplete phase 1 ESA0.3101320

JEvaluate consultants & contractors0.6101320

KObtain rough construction costs0.55815

LDetermine highest & best use0.5359

MIdentify debt options0.4248

NIdentify equity options0.5345

OUpdate financial underwriting0.5123

PReevaluate organization strategy0.6235

QEstimate schedule0.6347

RGain control of site and/or client0.6347

SReview and approve0.7347