Research on Construction Safety Risk Assessment of New Subway Station Close-Attached Undercrossing the Existing Operating Station

Table 14

Comparison of the third-level index data of “new subway station.”

Third-level index Risk assessment resultCorresponding risk grade of risk assessmentActual engineering measurement resultCorresponding risk grade of actual measurement Consistency

Information monitoring equipment failures (times/month)6.2Medium risk5.3Medium riskYes
Accuracy rate of feedback real-time data (%)87.5High risk93Medium riskNo
Horizontal and vertical displacement of retaining pile (wall) and top of slop (m)15Medium risk12Medium riskYes
Axial force of struts (pieces)6Low risk8Low riskYes
Anchor tension (pieces)7Low risk8Low riskYes
Ground settlement (m)2.5Low risk2Low riskYes
Clearance convergence of shaft support structure (m)4Medium risk5Medium riskYes
Monitoring hole of groundwater level (pieces)5Medium risk6Low riskNo
Survey spot arrangement spacing (m)12Medium risk9.5Low riskNo
Lateral displacement of space enclosing structure (mm)7.4Low risk4.9Low riskYes
Stratum filtering flow (permeability coefficient cm/s)2×105Medium risk3×105Medium riskYes
Sand content control (10000−1)0.8Medium risk0.9Medium riskYes
Depth of foundation pit (m)26High risk25.5High riskYes
Buried depth (m)24.2High risk24.2High riskYes
Impact of surrounding buildings on construction0.9Medium risk0.9Medium riskYes
Stiffness of initial support (N/)0.81Low risk0.92Low riskYes
Ground traffic control (thousand vehicles/h)5.1High risk6.2High riskYes
Noise control (dB)daytime67Low riskdaytime59Low riskYes
night29night 30
Sewage control (mg/L)293Medium risk262Medium riskYes
Light pollution control (W/)7Low risk6.2Low riskYes
Dust control (m)2.1Medium risk2.5Low riskNo
Construction trash control (%)12High risk18High riskYes
Impact on business climate (ten thousand person-time/month)15.8Medium risk12Medium riskYes