Research on Construction Safety Risk Assessment of New Subway Station Close-Attached Undercrossing the Existing Operating Station

Table 7

Index weight of construction safety risk assessment at all levels.

First-level index
(Weight)
Second-level indexWeight of second-level indexThird-level indexWeight of third-level index

A Existing subway station (0.5)A1 Station structure0.1599A120.0630
A130.1098
A150.3005
A160.5267
A2 Track structure0.4185A220.2000
A240.2000
A250.6000
A3 Power supply system0.2625A310.1667
A320.8333
A4 Water supply and drainage system0.0618A410.2000
A430.8000
A5 Ventilation and signal system0.0973A510.2389
A530.5495
A560.0650
A570.1466

B New subway station (0.5)B1 Construction monitoring of existing station0.3543B110.2295
B120.3305
B140.1040
B160.0444
B170.0444
B180.1557
B190.0684
B1100.0231
B2 New space enclosing structure0.1587B210.1667
B230.8333
B3 Engineering dewatering0.0676B310.2000
B330.8000
B4 Foundation pit excavation0.0448B420.6667
B440.3333
B5 Surrounding rock and soil mass and surrounding environment0.1036B510.1556
B520.0623
B530.0623
B540.0997
B550.2375
B580.3523
B590.0304
B6 Construction technology management of main structure0.2399B610.3777
B620.0916
B630.0916
B650.1528
B660.2449
B670.0413
B7 Green construction0.0312B720.0533
B740.1351
B750.3371
B760.0829
B770.2205
B780.1351
B790.0362