Monthly Unit Commitment Model and Algorithm with Renewable Energy Generation Considering System Reliability
| Scale | Results | Algorithm | AGA | GA | BBO |
| 10 units | optimal cost/107$ | 1.5037 | 1.5106 | 1.5137 | worst cost/107$ | 1.5525 | 1.5429 | 1.5525 | average cost/107$ | 1.5290 | 1.5366 | 1.5390 | time/s | 68 | 62 | 64 | reliable rate | 0.0883 | 0.0985 | 0.0993 |
| 20 units | optimal cost/107$ | 3.1003 | 3.1068 | 3.1163 | worst cost/107$ | 3.2806 | 3.2907 | 3.2904 | average cost/107$ | 3.2066 | 3.2512 | 3.2566 | time/s | 138 | 136 | 148 | reliable rate | 0.0916 | 0.1005 | 0.1016 |
| 40 units | optimal cost/107$ | 6.3677 | 6.3881 | 6.36907 | worst cost/107$ | 6.5470 | 6.5618 | 6.5660 | average cost/107$ | 6.4681 | 6.4870 | 6.4088 | time/s | 206 | 209 | 210 | reliable rate | 0.0897 | 0.1102 | 0.1097 |
| 60 units | optimal cost/107$ | 9.5410 | 9.5776 | 9.5561 | worst cost/107$ | 9.7963 | 9.8064 | 9.7988 | average cost/107$ | 9.6905 | 9.7173 | 9.7003 | time/s | 289 | 367 | 328 | reliable rate | 0.0812 | 0.0864 | 0.0822 |
| 80 units | optimal cost/107$ | 12.833 | 12.908 | 12.862 | worst cost/107$ | 13.345 | 13.679 | 13.447 | average cost/107$ | 13.069 | 13.240 | 13.165 | time/s | 363 | 488 | 420 | reliable rate | 0.1069 | 0.1573 | 0.1307 |
| 100 units | optimal cost/107$ | 16.017 | 16.099 | 16.087 | worst cost/107$ | 16.320 | 16.414 | 16.339 | average cost/107$ | 16.198 | 16.228 | 16.205 | time/s | 493 | 692 | 583 | reliable rate | 0.0993 | 0.1581 | 0.1229 |
|
|
Note: BBO is biogeography-based optimization algorithm.
|