Research Article
Intelligent Prediction of the Construction Cost of Substation Projects Using Support Vector Machine Optimized by Particle Swarm Optimization
Table 4
Prediction error of different models.
ā
GM (1,
n
)
SVM
PSO-SVM
PCA-SVM
PCA-PSO-SVM
MAPE
19.16%
17.10%
10.21%
11.57%
6.21%
RMSE
11.52
11.73
6.72
6.63
3.62