Research Article

A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 1

Monte Carlo simulation results.

DescriptionDeterministic probability ()Std.P80P100
Dev.(days)(days)

Pre-analysis554.27979988

Pre-mitigation< 124.961,1381,185

Post-mitigation< 126.561,0791,123