A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project
Table 2
Input data for case analysis.
| Activity | Subsequent activity | Duration (days) | Average time (days) t = (to+tm+tp)/3 | Crash time constraint (t - o) (days) | Crash time constraint (m -o) (days) | Crash time constraint (p -o) (days) | Fixed cost (1000USD) | o | m | p |
| J (Site Preparation) | B | 57 | 69 | 76 | 67 | 10 | 12 | 19 | 58 |
| A (Design and Subcontracting) | B | 107 | 119 | 131 | 119 | 12 | 12 | 24 | 2,453 |
| B (Piling) | C | 95 | 117 | 127 | 113 | 18 | 22 | 32 | 605 |
| C (Foundation) | D | 73 | 89 | 97 | 86 | 13 | 16 | 24 | 384 |
| D (RC 2F) | E | 59 | 73 | 79 | 71 | 11 | 14 | 20 | 1,500 |
| E (RC 3F) | F, G | 59 | 72 | 78 | 70 | 11 | 13 | 19 | 1,500 |
| F (RC 4F) | H | 58 | 72 | 79 | 70 | 12 | 14 | 21 | 1,500 |
| G (Arch. 2F) | H | 79 | 92 | 98 | 90 | 11 | 13 | 19 | 3,339 |
| H (Arch. 3F) | I | 59 | 72 | 78 | 70 | 11 | 13 | 19 | 3,339 |
| I (Arch. 4F to shelter &Outside) | - (FINISH) | 326 | 398 | 434 | 386 | 60 | 72 | 108 | 3,339 |
|
|
Note : o: optimistic; m: most likely; p: pessimistic. |