Research Article

A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 2

Input data for case analysis.

ActivitySubsequent activityDuration (days)Average time (days)
t = (to+tm+tp)/3
Crash time constraint (t - o) (days)Crash time constraint (m -o) (days)Crash time constraint (p -o) (days)Fixed cost (1000USD)
omp

J (Site Preparation)B5769766710121958

A (Design and Subcontracting)B1071191311191212242,453

B (Piling)C95117127113182232605

C (Foundation)D73899786131624384

D (RC 2F)E597379711114201,500

E (RC 3F)F, G597278701113191,500

F (RC 4F)H587279701214211,500

G (Arch. 2F)H799298901113193,339

H (Arch. 3F)I597278701113193,339

I (Arch. 4F to shelter &Outside)- (FINISH)32639843438660721083,339

Note: o: optimistic; m: most likely; p: pessimistic.