Research Article

A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 4

Project duration in case of different expected times.

ActivityAverage time (days)Optimistic time (days)Pessimistic Time (days)Most likely time (days)
Start timeProject durationStart timeProject durationStart timeProject durationStart timeProject duration

00100508570112201032
A119107131119
B232202258236
C318275355325
D389334434398
E459393512470
G549472610562
H619531688634
I100585711221032