Research Article
A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project
Table 5
Optimum project duration and crash plan in case of average time.
| Node | Start time (days) | Activity | Crash time (days) | Crash cost (USD) | Project crash cost (USD) | Project delay penalty cost (USD) |
| 1 | 0 | A | 0 | 0 | 133,500 | 0 | 2 | 119 | B | 10 | 50,000 | 3 | 222 | C | 13 | 53,500 | 4 | 295 | D | 0 | 0 | 5 | 366 | E | 0 | 0 | 6 | 436 | G | 0 | 0 | 7 | 526 | H | 0 | 0 | 8 | 596 | I | 6 | 30,000 | 9 | 976 | | | |
|
|