Research Article

A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 5

Optimum project duration and crash plan in case of average time.

NodeStart time
(days)
ActivityCrash time
(days)
Crash cost
(USD)
Project crash cost
(USD)
Project delay penalty cost
(USD)

10A00133,5000
2119B1050,000
3222C1353,500
4295D00
5366E00
6436G00
7526H00
8596I630,000
9976