A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project
Table 7
Optimum project duration and crash plan in case of pessimistic time.
| Node | Start time (days) | Activity | Crash time (days) | Crash cost (USD) | Project crash cost (USD) | Project delay penalty cost (USD) |
| 1 | 0 | A | 10 | 100,000 | 1,149,000 | 0 | 2 | 121 | B | 32 | 201,000 | 3 | 216 | C | 24 | 113,000 | 4 | 289 | D | 10 | 100,000 | 5 | 358 | E | 10 | 100,000 | 6 | 426 | G | 0 | 0 | 7 | 524 | H | 0 | 0 | 8 | 602 | I | 60 | 535,000 | 9 | 976 | | | |
|
|