A Hybrid Approach for Project Crashing Optimization Strategy with Risk Consideration: A Case Study for an EPC Project

Table 7

Optimum project duration and crash plan in case of pessimistic time.

NodeStart time
(days)
ActivityCrash time
(days)
Crash cost
(USD)
Project crash cost
(USD)
Project delay penalty cost
(USD)

10A10100,0001,149,0000
2121B32201,000
3216C24113,000
4289D10100,000
5358E10100,000
6426G00
7524H00
8602I60535,000
9976