Research Article
Profit Maximization for Waste Furniture Recycled in Taiwan Using Cradle-to-Cradle Production Programming
Table 2
The processing capacity for a unit of time.
| Categories of time available | Time |
| The amount of repaired waste furniture for a unit of time | 1,200 tons × 20 % = 240 tons 240 tons ÷ 704 = 0.34 tons/hour | The amount of disassembled waste furniture for a unit of time | 1,200 tons × 10 % = 120 tons 120 tons ÷ 352 hours = 0.34 tons/hour | The amount of coarsely crushed waste furniture for a unit of time | 1,200 tons × 30 % = 360 tons 360 tons ÷ 352 hours = 1.023 tons/hour | The amount of finely crushed waste furniture for a unit of time | 1,200 tons × 30 % = 360 tons 360 tons ÷ 352 hours = 1.023 tons/hour |
|
|