Research Article

Research on Construction and Application for the Model of Multistage Job Shop Scheduling Problem

Table 5

Comparison table of algorithm operation results in the second stage.

Workstation no.S1ā€²-S2 algorithmS1-S2 algorithm
Task no.Assembly time PkWaiting timeAssembly end time CklTask no.Assembly time PkWaiting timeAssembly end time Ckl

Assembly workstation 1Task 227027Task 227027
Task 917114131Task 1013.5113.5127

Assembly workstation 2Task 122022Task 122022
ā€‰Task 1013.5110.5124Task 68.5113.5122
Task 813120135

Assembly workstation 3Task 3202Task 3202
Task 419102121Task 917111128

Assembly workstation 4Task 7721082Task 41986.5105.5
Task 813122.5135.5Task 772119191

Assembly workstation 5Task 525.51843.5Task 525.5101126.5
Task 68.5115123.5