Research Article

Investment Risk Assessment of Dispersed Wind Power in Low Wind Speed Area Using a Hybrid Multi-Criteria Decision-Making Approach Based on Hesitant Fuzzy Linguistic Environment

Table 4

CRFs selected by five-dimensional risk analysis.

No.CRFsProbabilitySeverityUrgencyUncontrollabilityInfectiousnessNormalized impact

1Technical conditions for wind turbine556351.0000
2Policy subsidy risk446450.9519
3Grid connection risk555350.9448
4Regional absorptive capacity556250.8800
5Operation &maintenance risk645340.8684
6Demand risk of electricity consumption456250.8179
7Topographic conditions464340.8069
8Project construction risk645330.7896
9On-grid price risk545250.7693
10Operation &maintenance cost554330.7420
11Wind resource condition risk454250.7121
12Ecological damage risk455240.7121
13Impact on agriculture and tourism455240.7121
14Green power certificate risk345340.6860
15Climatic conditions543430.6860
16Public acceptance355240.6420
17Construction cost risk344340.6324
18Profitability risk344340.6324