Research Article
Regression-Based Prediction of Power Generation at Samanalawewa Hydropower Plant in Sri Lanka Using Machine Learning
Table 2
Power generation and the rainfall received from June to November of 2016.
| Month | Power (GWh) | Rainfall (mm) | Alupola (RF1) | Detanagalla (RF2) | Balangoda (RF3) | Nagarak Estate (RF4) | Belihuloya (RF5) | Nanperial (RF6) |
| Jun 2016 | 33.4 | 236 | 26 | 61 | 18 | 8 | 18 | Jul 2016 | 13.5 | 148 | 37 | 29 | 39 | 49 | 40 | Aug 2016 | 13.4 | 241 | 8 | 19 | 14 | 19 | 14 | Sep 2016 | 2.9 | 220 | 3 | 17 | 6 | 0 | 6 | Oct 2016 | 2.5 | 581 | 93 | 131 | 100 | 77 | 102 | Nov 2016 | 1.1 | 591 | 350 | 419 | 349 | 518 | 358 |
|
|