Application of Service Modular Design Based on a Fuzzy Design Structure Matrix: A Case Study from the Mining Industry

Table 4

Semantics of temporal relations and expression of triangular fuzzy numbers.

RelationshipTemporal correlationFuzzy semanticsTriangular fuzzy number

Parallel is executed before , but the result of execution has nothing to do with .Weak(0, 0.1, 0.3)
Overlapping is executed before , and the partial execution result of the first can create conditions for the second.Unimportant(0.2, 0.3, 0.4)
Sequential must precede and create conditions for .Common(0.4, 0.5, 0.6)
Cycle must precede and circulate once to create conditions for each other.Important(0.6, 0.7, 0.8)
Coupled and go back and forth many times to create conditions for each other.Very important(0.8, 0.9, 1)