Structural Optimization Design of Ship Lock Heads on Soft Soil considering Time-Varying Effects of the Structure and Foundation
Table 3
Ship lock construction process.
| Construction sequence | Construction process | Construction duration (day) | Construction intermissions (day) |
| C1 | Pouring bottom plate | 2 | 8 | C2 | Removing bottom plate formwork | 1 | 35 | C3 | Backfilling the first layer of soil | 20 | 96 | C4 | Pouring the corridor layer | 1 | 10 | C5 | Removing corridor layer formwork | 1 | 25 | C6 | Backfilling the second layer of soil | 19 | 26 | C7 | Pouring the empty-box layer | 1 | 9 | C8 | Removing empty-box layer formwork | 1 | 53 | C9 | Pouring the second-stage concrete | 1 | 8 | C10 | Removing the second-stage concrete formwork | 1 | 20 | C11 | Backfilling the third layer of soil | 18 | 30 |
|
|