Research Article

Biobjective Optimization-Based Frequency Regulation of Power Grids with High-Participated Renewable Energy and Energy Storage Systems

Table 6

Result comparison of online optimization under different disturbances.

Method|ACE| (MW) (Hz)CPS1 (%)Deviation (MW)Accuracy (%)Payment ($)
AvgMaxAvgMaxAvgMin

70 MWPROP0.8911.174.78E − 045.73E − 03199.99199.82550.0681.34165.58
SPEA20.8811.064.52E − 045.67E − 03199.99199.82383.3681.87130.09

−50 MWPROP0.648.093.46E − 044.15E − 03199.99199.90426.1481.1997.87
SPEA20.616.933.04E − 043.58E − 03199.99199.9353.3682.87126.95

Disturb 1 (see Figure 8(a))PROP4.7211.332.38E − 035.81E − 03199.96199.812854.3874.23816.35
SPEA24.429.952.24E − 035.12E − 03199.96199.851544.5782.73632.56

Disturb 2 (see Figure 9(a))PROP1.928.098.71E − 044.15E − 03199.99199.901240.6970.31311.12
SPEA21.826.958.01E − 043.59E − 03199.99199.93411.5678.75281.25