Construction Safety Risk Assessment of Large-Sized Deep Drainage Tunnel Projects

Table 2

Primary construction safety risk index system of the LSDDTP.

Secondary indexMain sewage tunnel projectShaft project

A: MenA11: weak safety awareness of shield engineering management personnelA21: weak safety awareness of shaft engineering management personnel
A12: insufficient safety skills of construction personnel in shield engineeringA22: insufficient safety skills of construction personnel in shaft engineering
A13: improper safety protection of construction personnel in shield engineeringA23: improper safety protection of construction personnel in shaft engineering
A14: failure to rectify potential safety hazards of shield engineeringA24: failure to rectify potential safety hazards of shaft engineering

B: MechanicalB11: unreasonable selection of shield machineB21: unreasonable selection of hoisting machinery
B12: unreasonable replacement of cutter headB22: verticality deviation of shaped steel mold
B12: failure of segment assembly system of shield machineB23: collision between grab bucket and pit wall
B14: failure of propulsion system of shield machineB24: unreasonable drilling rig selection

C: MaterialC11: damaged segmentC21: imperfect anchor pipe grouting
C12: unqualified segmentC22: insufficient grid reinforcement
C13: unqualified grouting materialsC23: improper stacking of materials in shaft operation platform
C14: unreasonable segment hoisting processC24: calculation error of slurry solidification time

D: MethodD11: immature split origination technologyD21: immature reverse technique
D12: immature construction technology of secondary liningD22: piping phenomenon
D13: unreasonable safety measures for shield constructionD23: unreasonable safety measures for shaft construction
D14: unreasonable safety investment in shield constructionD24: unreasonable safety investment in shaft construction
D15: backward installation technology of negative loop segmentD25: unreasonable layout of dewatering well
D16: error in setting shield tunnelling parametersD26: error in setting drilling rig parameters

E: EnvironmentE11: failure to effectively detect the changes in the surrounding environment of tunnel engineeringE21: failure to effectively detect the changes in the surrounding environment of shaft project
E12: failure to deal with the changes in the surrounding environment of tunnel engineering in timeE22: failure to deal with the changes in the surrounding environment of shaft engineering in time
E13: incomplete engineering geology and hydrologyE23: adverse effects of surrounding structures and buildings
E14: undiscovered natural holesE24: excessive groundwater level
E15: undiscovered weak stratumE25: liquefaction deformation of soil mass