Integration of Interpretive Structural Modeling with Fuzzy Bayesian Network for Risk Assessment of Tunnel Collapse

Table 12

Sensitivity analysis result.

Risk factorProbability of occurrence (%)Original collapse probability (%)New collapse probability (%)Probability change (%)

Excessive construction disturbance21.217.731.113.4
Insufficient support strength15.417.730.212.5
Improper construction measures or poor quality14.017.720.32.6
Unreasonable design7.717.719.92.2
Untimely support14.617.718.71.0
Severe bias10.817.718.60.9
Irregular construction23.417.718.50.8
Low level of management awareness16.017.718.30.6
Poor stability of surrounding rock65.117.718.00.3
Special poor geological conditions26.517.718.00.3
Failure of monitoring and measurement standards6.817.717.80.1
Atmospheric rainfall27.117.717.80.1
Shallow buried15.417.717.70.0
Mutation of geological conditions7.117.717.70.0
Groundwater seepage32.417.717.70.0
Inaccurate geological survey15.717.717.70.0
Inadequate advance geological forecast4.417.717.70.0