Research Article

Single-Machine Scheduling with Fixed Periodic Preventive Maintenance to Minimise the Total Weighted Completion Times

Table 5

Comparison results of the Krim model and our model.

n
AveSolAveLBNoptAveSolAveLBNopt

5637.763637.76380 (80)637.763637.76380
6916.075916.07580 (80)916.075916.07580
71123.3881123.38880 (80)1123.3881123.38880
81497.7251497.72580 (80)1497.7251497.72580
91808.9131808.91380 (80)1808.9131808.91380
102210.2002210.20080 (80)2210.2002210.20080
112623.4502623.45080 (80)2623.4502623.45080
123091.4753091.47580 (80)3091.4753091.47580
133528.4253446.01379 (53)3528.4133528.41380
144155.1753469.96377 (9)4153.6254153.62580
154729.3253369.71376 (1)4724.0134724.01380
207875.8632942.80020 (0)7862.4387622.03833
2512471.2252464.22510 (0)12368.56311775.16315