Research Article
Single-Machine Scheduling with Fixed Periodic Preventive Maintenance to Minimise the Total Weighted Completion Times
Table 8
Average performance for lower bounds compared to the optimal solutions.
| n | Average RPG (%) | LB1 | LB3 | LB4 | LB5 | NewLB |
| 5 | 11.947 | 9.513 | 48.148 | 46.910 | 2.226 | 6 | 12.464 | 9.288 | 55.263 | 54.284 | 2.759 | 7 | 13.316 | 9.493 | 58.758 | 58.073 | 3.933 | 8 | 14.218 | 9.818 | 62.607 | 61.635 | 4.425 | 9 | 14.554 | 9.848 | 64.509 | 63.854 | 5.268 | 10 | 14.799 | 9.845 | 67.260 | 66.112 | 5.774 | 11 | 15.016 | 10.099 | 68.983 | 68.205 | 5.867 | 12 | 15.479 | 10.335 | 70.491 | 69.965 | 6.818 | 13 | 15.496 | 10.249 | 71.310 | 70.676 | 7.130 | 14 | 15.762 | 10.520 | 73.080 | 72.128 | 7.389 | 15 | 16.039 | 11.085 | 73.560 | 72.583 | 7.845 | Overall average | 14.463 | 10.008 | 64.906 | 64.039 | 5.403 |
|
|