Soil-Structure Interaction of Flexible Temporary Trench Box: Parametric Studies Using 3D FE Modelling
Table 5
Construction sequence of FE modelling for sensitive blue clay in PLAXIS-3D.
Phase
In the model
Drainage
Phase 0
Only soil elements (no structure)
procedure
Phase 1
Excavation (1st layer, depth: 0.6 m) fissured brown clay
Drained
Phase 2
Excavation (2nd layer: 0.6 to 2 m) brown clay
Plastic: undrained B1 (soil model)
Phase 3
Adding structural element
Plastic: undrained B1 (soil model)
Phase 4
Excavation (3rd layer: 2 m to 6 m) sensitive blue clay
Plastic: undrained B1 (soil model)
1In the undrained (B) drainage type, modelling of undrained behaviour using effective parameters for stiffness and undrained shear strength parameters is allowed.