Research Article

The Intelligence of Octagonal Fuzzy Number to Determine the Fuzzy Critical Path: A New Ranking Method

Table 2

Total fuzzy slack time for each path in fuzzy project network.

PathTotal fuzzy slack time (, , ) Total fuzzy slack time (, , )

1-2-4-7 (0, 8, 81) (81, 0, 89)
1-2-5-7 (0, 0, 71) (71, 0, 71)
1-5-7 (0, 10, 51) (51, 10, 28)
1-3-5-7 (0, 0, 63) (63, 0, 63)
1-3-6-7 (0, 0, 65) (65, 0, 65)