Research Article

CFD Application to Hydrogen Risk Analysis and PAR Qualification

Table 1

Arrangement of recombiners.

LocationTypeNo.

PZR relief tank roomFR90/1–15003
Surge line roomFR90/1–9601
PZR roomFR90/1–9601
No. 1 SG compartmentFR90/1–15003
No. 2 SG compartmentFR90/1–15003
No.1 RCP roomFR90/1–9601
No.1 RCP roomFR90/1–9601
SIT roomFR90/1–9601
Dome regionFR90/1–15004
Annular compartmentFR90/1–15004