An Evaluation of SMR Economic Attractiveness

Table 2

Scenario input data for Monte Carlo simulation.

InputPDF LR SMR

Overnight construction cost (€/kWe)Triangular2000; 4000; 3000
(min; max; most likely)
Estimated from LR capital costs [10]
“External” delay in construction scheduleUniform0; 36; 18 months
(min; max; mean)
0; 36; 18 months
(min; max; mean)
Plant availabilityTriangular80%; 95%; 95%
(min; max; most likely)
80%; 95%; 95%
(min; max; most likely)
Operation and maintenance cost (€/MWh)Uniform6.3; 11.7; 9.0
(min; max; mean)
120% of LR
Fuel cycle cost ($/MWh)Uniform4.7; 8.6; 6.7
(min; max; mean)
4.7; 8.6; 6.7
(min; max; mean)
Decontam. & decommissioning sinking fund ($/MWh)Uniform1.4; 2.6; 2
(min; max; mean)
200% of LR
Electricity price (€/MWh)Triangular50; 90; 70
(min; max; most likely)
50; 90; 70
(min; max; most likely)
Financial interest rateUniform6.0%; 8.0%; 7.0%
(min; max; mean)
6.0%; 8.0%; 7.0%
(min; max; mean)