Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms
Table 6
NPP EVMS standard procedures for system development.
| Description (S-) | Method and procedure | Technique |
| Budget (SB) | SBD: standard estimate database SBE: project estimate SBB: project budget | (i) Knowledge embedding (ii) Self-evolving  (iii) Future extension to BIM |
| PV (SP) | SPA: top-down Qty based assignment SPW: standard weighted milestones | (i) Earned standards (ii) Simplified resources |
| EV (SE) | SEV: rolling up EVs based on Qty SES: existing scheduling system | (i) Target progress concept (ii) Activities not connected to cost |
| AC (SA) | SAC: decomposed cost from ERP SAA: existing accounting system (ERP) | (i) Quantity and resource related (ii) Generic accounting system |
|
|