Nuclear Power Plant Construction Scheduling Problem with Time Restrictions: A Particle Swarm Optimization Approach
| Construction time of the building of nuclear power plant | | | | | 46 | 50 | 39 | 35 | 25 | Preparation time (first) | | | | | 10 | 17 | 14 | 15 | 18 | Lower bound of time window | | | | | 73 | 85 | 78 | 84 | 92 | Upper bound of time window | | | | | 142 | 144 | 138 | 163 | 169 | Preparation time (dependent) | | | | | 0 | 11 | 17 | 15 | 12 | 9 | 0 | 9 | 12 | 9 | 15 | 11 | 0 | 15 | 13 | 17 | 8 | 8 | 0 | 18 | 11 | 9 | 8 | 10 | 0 | Reactor installation time | | | | | 34 | 41 | 29 | 38 | 18 | Reactor installation time (dependent) | | | | | 0 | 29 | 41 | 36 | 36 | 43 | 0 | 47 | 36 | 36 | 29 | 50 | 0 | 50 | 30 | 24 | 29 | 48 | 0 | 41 | 36 | 44 | 25 | 22 | 0 | Weight of order | | | | | 2 | 2 | 1 | 2 | 2 |
|
|