Nuclear Power Plant Construction Scheduling Problem with Time Restrictions: A Particle Swarm Optimization Approach

Table 2


Construction time of the building of nuclear power plant
4650393525
Preparation time (first)
1017141518
Lower bound of time window
7385788492
Upper bound of time window
142144138163169
Preparation time (dependent)
011171512
909129
151101513
1788018
1198100
Reactor installation time
3441293818
Reactor installation time (dependent)
029413636
430473636
295005030
242948041
364425220
Weight of order
22122