The Investigation of Nonavailability of Passive Safety Systems Effects on Small Break LOCA Sequence in AP1000 Using RELAP5 MOD 4.0
Table 1
Actuation set-points and time delay assumption considered for AP1000 LOCA [
4].
| System/function | Actuation set-points | Time delay (sec) |
| Reactor trip | 12.41 MPa | 2 | “S” signal generation | 11.72 MPa | 2 | SG feedwater valves start closing | After reactor trip signal | 3.2 | Main steam isolation valves start closing | After “S” signal | 4.8 | Reactor coolant pumps trip | After “S” signal | 6 | PRHRS isolation valve opens | After “S” signal | 0 | CMT actuation | After “S” signal | 0 | Accumulator actuation | 4.83 MPa | 0 | ADS-1 actuation | After CMT water volume reduces to 67.5% | 20 | ADS-2 actuation | 70 s after ADS-1 actuation | 30 | ADS-3 actuation | 120 s after ADS-2 actuation | 30 | ADS-4a actuation | 20.0% liquid volume fraction in CMT | 2 | ADS-4b actuation | 60 s after ADS-4a actuation | 2 | IRWST injection | Pressure < 89.6 kPa + containment pressure | 2 |
|
|