Estimation of closed nuclear energy system costs (unit: M$ based on 2016 USD).

ParametersCFC-1CFC-2

Number of PWRs3131
Number of PHWRs44
Minimum number of SFRs needed2515
SFR’s CR0.60.46
Operating lifetime (PWR/PHWR/SFR)60/50/8060/50/80
SFR overnight cost91,61454,968
PWR overnight cost171,955171,955
PHWR overnight cost3,3293,329
SFR fuel cost108,22234,861
PWR fuel cost120,012120,012
PHWR fuel cost23,99023,990
SFR O&M cost4,8862,932
PWR O&M cost9,6049,604
PHWR O&M cost218218
SFR D&D cost9,7725,863
PWR D&D cost19,20819,208
PHWR D&D cost435435
Closed nuclear energy system cost563,246447,376
Electricity generation (TWh)28,84125,035