(ON = 1 and OFF = 0) switching operation mode for (W, D, C, and P) facility options in Barakah site.

Operation mode optionsBarakah-1Barakah-2Barakah-3Barakah-4
WDCPWDCPWDCPWDCP

Option 10001000100010001
Option 20010001000100010
Option 30011001100110011
Option 40100010001000100
Option 50101010101010101
Option 60110011001100110
Option 70111011101110111
Option 81000100010001000
Option 91001100110011001
Option 101010101010101010
Option 111011101110111011
Option 121100110011001100
Option 131101110111011101
Option 141110111011101110
Option 151111111111111111

W = wet storage (SFPI), D = dry storage (ISFSI), C = CDS, and P = PDF.