Technical Options and Cost Estimates for Spent Nuclear Fuel Management at the Barakah Nuclear Power Plants

Table 3

Spent fuel generation status of Barakah site.

Barakah site
Unit #1234

Construction (yr)2012201320142015
Commercial operation (yr)2020202220232024
Design life expiration (yr)2080208220832084
Refuelling cycle (month)18181818
In-core fuel (FAs)241241241241
SFP capacity (FAs)780780780780
SFP storage for year 2020 (FAs)1333.41333.41333.41333.4
SFP storage for year 2040 (FAs)2666.82666.82666.82666.8
SFP storage for year 2060 (FAs)4174.54174.54174.54174.5

Expectation.