Technical Options and Cost Estimates for Spent Nuclear Fuel Management at the Barakah Nuclear Power Plants
Table 6
Spent fuel transportation schedule showing effect of SFPI and ISFSI facility shifting times for all scenarios.
| SFPI | Barakah-Sc.1 | Barakah-Sc.2 | Barakah-Sc.3 | Start | Finish | Start | Finish | Start | Finish |
| NPP shutdown | 6/1/2080 | | 6/1/2080 | | 6/1/2080 | | Transition | 6/1/2080 | 6/1/2085 | 6/1/2080 | 6/1/2085 | 6/1/2080 | 6/1/2085 | D & D | 6/1/2085 | 6/1/2091 | 6/1/2085 | 6/1/2091 | 6/1/2085 | 6/1/2091 | SFPI operation | 6/1/2087 | 6/1/2107 | 6/1/2087 | 6/1/2127 | 6/1/2087 | 6/1/2107 | SNF transfer to CDS | 6/1/2105 | 6/1/2107 | 6/1/2125 | 6/1/2127 | 6/1/2105 | 6/1/2107 | SFPI D & D | 6/2/2107 | 6/2/2108 | 6/2/2127 | 6/2/2128 | 6/2/2107 | 6/2/2108 | Site remediation | 6/2/2108 | 6/1/2110 | 6/2/2128 | 6/1/2130 | 6/2/2108 | 6/1/2110 | Site open | 6/1/2110 | 6/1/2110 | 6/1/2130 | 6/1/2130 | 6/1/2110 | 6/1/2110 |
| ISFSI | NPP shutdown | 6/1/2080 | | 6/1/2080 | | 6/1/2080 | | Transition | 6/1/2080 | 6/1/2085 | 6/1/2080 | 6/1/2085 | 6/1/2080 | 6/1/2085 | SNF transfer to ISFSI | 6/1/2085 | 12/1/2087 | 6/1/2085 | 12/1/2087 | 6/1/2085 | 12/1/2087 | D & D | 12/1/2087 | 12/1/2093 | 12/1/2087 | 12/1/2093 | 12/1/2087 | 12/1/2093 | ISFSI operation | 12/1/2089 | 12/1/2109 | 12/1/2089 | 12/1/2109 | 12/1/2089 | 12/1/2129 | SNF transfer to CDS | 1/1/2107 | 1/1/2109 | 1/1/2107 | 1/1/2109 | 1/1/2127 | 1/1/2129 | Site remediation | 12/1/2110 | 12/1/2112 | 12/1/2110 | 12/1/2112 | 12/1/2130 | 12/1/2132 | Site open | 12/1/2112 | 12/1/2112 | 12/1/2112 | 12/1/2112 | 12/1/2132 | 12/1/2132 |
|
|