Research Article
Studies on Optimal Strategy to Adopt Nuclear Power Plants into Saudi Arabian Energy System Using MESSAGE Tool
Table 7
Capital cost category estimate for the candidate NPPs assumed in this study [
46–
58].
| Category | Unit | % of total | APR-1400 | SMART-100 |
| Direct construction costs | | | | | Equipment | U$/kW | 15 | 857.1 | 1500 | Labor | U$/kW | 14 | 800 | 1400 | Materials | U$/kW | 4 | 228.6 | 400 | Direct construction subtotal | U$/kW | 33 | 1885.6 | 3300 | Indirect services costs | | | | | Off-site engineering and design | U$/kW | 13 | 742.8 | 1300 | On-site project management | U$/kW | 10 | 571.4 | 1000 | Other on- and off-site indirect services | U$/kW | 14 | 800 | 1400 | Indirect services subtotal | U$/kW | 37 | 2114.2 | 3700 | Direct and indirect construction subtotal | U$/kW | 70 | 3999.8 | 7000 | Preconstruction costs | | 2 | 114.3 | 200 | Owner’s costs | | 10 | 571.4 | 1000 | Supplementary costs | | 1 | 57.1 | 100 | Financing during construction | | 17 | 971.4 | 1700 | Total capital costs | U$/kW | | 5714 | 10000 |
|
|