Importance of the PSFs for NPP decommissioning derived through the Fuzzy-AHP.
| Level 1 | Level 1 weight | Level 2 | Level 2 weight | Influential factors | Weight of influential factor |
| Human | 2.30E − 01 | Stress | 1.50E − 01 | Work stress | 5.23E − 02 | Team stress | 4.93E − 02 | Individual stress | 4.78E − 02 | Emotional state | 8.05E − 02 | Excitement | 1.93E − 02 | Boredom | 1.77E − 02 | Frustration | 2.17E − 02 | Dissatisfaction | 2.17E − 02 |
| Operation | 4.50E − 01 | Work process design | 1.40E − 01 | Decommissioning technique | 4.60E − 02 | Equipment selection | 3.49E − 02 | Worker safety | 5.86E − 02 | Team factor | 1.49E − 01 | Response based on the work situation | 4.31E − 02 | Leadership | 3.27E − 02 | Communication and decision making | 3.86E − 02 | Team workload | 3.42E − 02 | Working condition | 1.62E − 01 | Discomfort | 4.05E − 02 | Equipment arrangement | 5.35E − 02 | Working environment | 6.80E − 02 |
| Ergonomic system | 3.20E − 01 | Equipment maintenance | 6.08E − 02 | Part replacement condition | 2.92E − 02 | Equipment maintenance cycle | 3.16E − 02 | Operation complexity | 2.59E − 01 | Procedure availability | 1.27E − 01 | Equipment operation | 1.32E − 01 |
| Total | 1 | Total | 1 | Total | 1 |
|
|