Evolution Balancing of the Small-Sized Wheel Loader Assembly Line

Table 1

Precedence relation between assembly tasks.

TaskA1A2A3A4A5A6A7A8A9A10

Predecessor(s)A1, A2, A3A4A5A6A6
Duration41424039394836362830
Operators assigned564101423111

TaskA11A12A13A14A15A16A17A18A19A20

Predecessor(s)A6, A9, A10, A11A12A13A13A13A13A14, A15, A16, A17A18A18
Duration35141312151815587
Operators assigned1111111111

TaskA21A22A23A24A25A26A27A28A29A30

Predecessor(s)A18A19, A20, A21A22A18, A23A23A18A25, A26A23A23A23
Duration7711231748242231
Operators assigned1111111111