Influence of Blasting Vibration on Young Concrete Bridge: A Case Study of Yesanhe Super Large Bridge

Table 1

PPV and main frequency of the bridge under blasting tests.

Explosion sourcePierNumber of monitoring pointsLocation of monitoring pointsVertical PPV (cm/s)Vertical main frequency (Hz)Horizontal PPV (cm/s)Horizontal main frequency (Hz)

Intake slope4# pier5#Pier foundation0.0339.10.0922.3
7#Edge of box girder0.0339.10.1117.4
8#Edge of box girder0.0331.30.1617.4
9#Center of box girder0.0345.30.0836.3
10#Edge of box girder0.1231.30.217.4
3# pier11#Pier foundation0.0331.30.0426
12#Edge of box girder0.0428.40.0526
13#Edge of box girder0.0641.70.0734.7

Right abutment4# pier5#Pier foundation0.0331.30.0325.8
6#Pier foundation0.0326.30.0726.3
8#Edge of box girder0.0726.30.125
10#Edge of box girder0.0122.70.0917.2
3# pier11#Pier foundation0.0321.70.0326.3
12#Edge of box girder0.0926.30.0926.3

Left abutment4# pier5#Pier foundation0.0315.60.0413
6#Pier foundation0.0315.70.0411.2
8#Edge of box girder0.1626.10.1415.7
9#Center of box girder0.0939.10.0819.6
10#Edge of box girder0.0139.10.0826
3# pier11#Pier foundation0.0619.50.0911.2
12#Edge of box girder0.1439.10.0411.2
13#Edge of box girder0.32200.0913
19#Pier foundation0.07260.0439.1
20#Inside of box girder0.139.10.1919.2