Construction Process Simulation and In Situ Monitoring of Dendritic Structure on Nanjing Niushou Mountain

Table 1

Division of construction stages.

StageNameReason

1Hoisting emplacementIn this stage, the pin joint was subjected to vertical shear force generated by gravity.
2Lower cable fixationIn this stage, the pin joint was subjected to horizontal shear force generated by horizontal components of active cable.
3Out-of-plane disturbanceIn the process of lifting, there might be out-of-plane disturbance. The pin joint was subjected to horizontal shear force generated by horizontal components of active cable; at the same time, the joints were subjected to out-of-plane loads due to out-of-plane disturbances.