Research Article

Analysis of the Risk Path of the Pipeline Corridor Based on System Dynamics

Table 2

Comprehensive pipeline gallery risk system.

Primary riskSecondary risk

Management team risk R1Team information level r1
Team personnel level r2
Personnel safety awareness level r3
Information management level r4
Personnel mental state r5

Environmental factor risk R2Geological disaster impact r6
Illegal invasion of people and animals r7
Third-party construction damage r8
Temperature, humidity, and chemical gas concentration in the corridor r9

Ingress pipeline risk R3Pipeline leak r10
Valves, pipe fittings, etc., are not maintained in time r11
Cracks, pipeline deviation, pipeline slippage, etc., caused by uneven settlement r12
Explosion and fire caused by pipeline r13

Auxiliary facility risk R4Lighting, ventilation, and drainage facilities r14
Above-ground and underground information is not linked r15
Risk sensing facilities in the corridor r16

Risk of pipe gallery R5Design and construction do not meet operation and maintenance requirements r17
Uneven settlement caused by construction problems cited r18
Unreasonable overall construction design r19
Information transfer between management center and gallery r20