Abstract

We aim at the problem of the large deformation and difficult control of surrounding rock when passing through a fault fracture zone in the centralized rail transportation lane along the south wing of Xinyi Coal Mine; the stress environment and failure mechanism of surrounding rock are analyzed through field investigation, numerical simulation, and field industrial test. The instability of the surrounding rock in the fault fracture zone was considered to be the result of the joint effect of the surrounding rock fracture development, lithology differences, water gushing occurrences, low strength of the original support, high in situ stress, and fault-related tectonic stress. Rock blocks are collected on site at the fracture zone, and the remoulded samples are prepared for mechanical experiments in the laboratory. The basic mechanical parameters of the roadway passing through silty mudstone, sand-mudstone interlayer, and fine sandstone were analyzed. A three-dimensional model is established to analyze the distributions of the stress, deformation, and plastic area in the surrounding rock mass after the tunnel passes through, considering both a single-rock mass and a multilayer-rock mass. Based on the above analysis, the “closed support + shotcrete + grouting + anchor mesh cable coupling support” is proposed. Three stations were arranged on site to observe the mine pressure, and the field industrial test shows that, within the 100 days of observation, the maximum roof-to-floor convergence is 38 mm, while the maximum horizontal convergence is 56 mm. The overall reinforcement effect of the roadway is good, the surface is smooth, and there is no phenomenon of concrete cracking and bolt fracture.

1. Introduction

In the process of coal mine roadway driving, it is often encountered with fault and fracture zone and other unfavorable geological strata, which have the characteristics of structural development, low strength, high water permeability, easy deformation, and other soft rocks. The bearing capacity of the rock mass in the fault fracture zone is weak, the lithology is complex, the support is difficult, the stress distribution in the fault fracture zone is complex, and the mine pressure law is variable, which seriously threatens the safety of the construction process.

At present, scholars at home and abroad have done a lot of research on the surrounding rock support of the roadway in the fault fracture zone and achieved some results [14]. Zhang et al. [5] studied the construction geological guarantee and surrounding rock control technology of the roadway in the super large fault area based on the engineering background of the safe excavation of the main transport roadway passing through the fault zone. Xiao et al. [6] studied the rule of the influence of fault zone on the mining roadway through the method of experiment and numerical calculation, which provided the basis for the reasonable arrangement and effective control of the roadway near the fault. Zhao et al. [7] summarized the application experience of the advanced pipe shed grouting support technology in the roadway support by studying the deformation control of the broken surrounding rock when the roadway passes through the complex fault zone. Wang et al. [8] used the yielding type anchor cable box girder support system in the fault area of the coal roadway to realize “control first, then resistance,” which not only played the role of the support system but also gave full play to the self-bearing capacity of the surrounding rock. Hao et al. [9] put forward the control measures of blot + mesh + anchor supporting measures to realize supports with strength, stiffness, and the structure, so as to achieve the stability control in deep soft roadway excavation. Zhang [10] put forward the support principle of “two high and one large” in view of the large deformation of the fault broken coal and rock roadway. Yan et al. [11] studied the surrounding rock control technology of the roadway in the fault area on the aquifer and proposed that “advance grouting, shotcreting and anchoring grouting stage reinforcement is the foundation support, and then the key parts of anchor cable reinforcement and surrounding rock grouting technology are implemented.” Meng et al. [12] put forward the technical scheme of “primary steel mesh spraying + reinforced concrete lining + secondary grouting” combined support for the difficult problem of roadway passing through faults under complex geological conditions. Song et al. [13] used the theory of ultralow friction effect of rock mass and the theory of dynamic load stress wave to study the influence of dynamic load on fault fracture zone and put forward the corresponding safety measures of roadway passing through fault. In view of the floor heave problem in the south wing area of Yangcheng Coal Mine, Wang et al. [14] proposed to optimize the full-face support by adopting the support technology of bolt mesh shotcrete and concrete filled steel tube. Kang et al. [15] analyzed the deformation characteristics of surrounding rock of roadway in ultra-kilometer-deep mine and put forward supporting measures. Jia and Wang [16] analyzed the deformation and failure mechanism of weak surrounding rock and proposed a buffering gradual change type double strength shell support method suitable for soft rheological rock mass. Meng et al. [17] analyzed the distribution characteristics of surrounding rock support stress field caused by anchor bolt and anchor cable under different preload and spacing and proposed a step-by-step combined support scheme of bolt mesh cable spraying + U-shaped steel support + grouting + floor bolt grouting for soft rock roadway. He and Zhang [18] aimed at the problem of surrounding rock stability control of deep broken soft rock roadway and proposed a multilevel bolt shotcrete combined support system with high-strength bolt dense support, new spray layer structure surface protection, and lag grouting reinforcement. Li et al. [19] studied the relationship between the failure area of circular roadway, residual strength of stratum, and support pressure in isotropic homogeneous stratum. The above research has carried on the correlation research to the tunnel passing through the fault instability mechanism and the control technology, but, to the tunnel passing through the fault and the weak rock zone surrounding rock instability mechanism and the control technology that still needs to be further explored, especially to the fault fracture zone surrounding rock mechanical characteristic, researches are few.

Based on the previous research results and methods, aiming at the problems of large deformation and difficult control of surrounding rock when passing through the fault fracture zone and soft rock zone in the driving process of the centralized rail transport roadway in the south wing of Xinyi Coal Mine, this paper puts forward the methods of field investigation, laboratory mechanical test, numerical simulation, and theoretical analysis to analyze the instability mechanism of surrounding rock in the fracture zone and puts forward that the form of “closed support + shotcrete + grouting + anchor mesh cable coupling support” is introduced, and the industrial test is carried out in the field.

2. Engineering Background

Xinyi Coal Mine is located in the northwest of Yanzhou City, Shandong Province, China. The mining area is about 4 km long in the northwest and 4 km wide in the northeast with an area of about 11.7 km2. The surface topography of the mining area is flat, and there are no rivers or lakes on the surface of the mining area. The ground elevation is 47.0∼50.0 m. The faults in the mine field are relatively developed, mainly tensile, and torsional normal faults, and most of them strike NNE or NE. The excavation of Xinyi Coal Mine’s south wing centralized rail transportation lane passed through three faults, and the strata are soft rock layers such as silty mudstone, sandy mudstone, and fine sandstone. The fractures of the fault fracture zone in the surrounding rock are developed, and there is angular sand gushing out from the fault, which has a great impact on the stability of the surrounding rock of the roadway. The thickness of the silty mudstone is 11 m, and the silty mudstone is easily broken into pieces by hard objects. The main component of the silty mudstone is clay minerals, with a small amount of silty sand. After one month of anchor mesh support in the early stage of excavation, the roadway has obvious section shrinkage, and the roof subsidence is serious, as shown in Figure 1(a).

The thickness of the interbedded sandstone-mudstone layer is 12 m, and this layer is composed of a large number of light green grey mudstones mixed in siltstone, with horizontal bedding, which is easily broken into pieces in the roadway. After excavation and disturbance, the cracks develop and expand when encountering water. The deformation of the roof is large, and there is a net pocket phenomenon. The anchoring force of the anchor bolt used for support in the early stage is seriously relaxed, as shown in Figure 1(b). The thickness of the fine sandstone is 14 m, and the fine sandstone is light grey, with quartz, feldspar, and calcic argillaceous cementation. Although the strength of fine sandstone is high, its integrity is greatly damaged due to being in the fault fracture zone. Compared with the silty mudstone and sandy mud interbedded roadways, the mine pressure is not particularly obvious, and the roadway deformation is small under the early support, as shown in Figure 1(c).

3. Physical and Mechanical Experiment of Rock

3.1. Sample Preparation

Because the fractures of the interbedded silty mudstone and sand mudstone are well developed, the degree of cementation is loose, and the rock is easily weathered and disintegrated, softens rapidly when encountering water, and was argillized; thus, it is difficult to process it into standard samples. Therefore, in this paper, the rock samples with developed fractures are processed into remoulded samples meeting the rock mechanics experimental standard. The denser and harder fine sandstone can be processed directly into standard samples.(1)Fine sandstone sample. Intact rock blocks with a size of approximately 200 mm × 200 mm × 200 mm were collected on site and transported back to the laboratory for processing into eight standard cylindrical samples with a size of φ50 × 100 mm (three uniaxial compression samples C1∼C3 and five triaxial compression samples C4∼C8) and three Brazilian split samples with a size of φ50 × 25 mm (C9∼C11).(2)Remoulded sample of silty mudstone and sand-mudstone interlayer. The preparation method is as follows: crush the original rock samples collected on site into crushed stone with a particle size of 50 mm; grind in a ball mill for 3 min, and filter the rock powder with a 200-mesh sieve; weigh the rock powder pass M, and add 5% M of rock powder to water and stir uniformly; put the mixture into the mould and stabilize it for 30 min with an axial pressure of 200 kN on a press; take out the samples to determine the compression ratio, make a standard reshaped sample, and dry the samples. Among them, there are eight remoulded silty mudstone samples (three uniaxial compression samples A1–A3 and five triaxial compression samples A4–A8) and Brazilian split samples of φ50 × 25 mm (a total of three samples A9–A11). There are a total of eight remoulded sandstone-mudstone interbedded rock samples (three uniaxial compression samples B1–B3 and five triaxial compression samples B4–B8) and Brazilian split samples of φ50 × 25 mm (a total of three samples B9–B11). A prepared partially remoulded sample is shown in Figure 2.

3.2. Test Design

(1)Brazilian splitting test: Displacement control (at a rate of 0.05 mm/s) is used to apply load to the specimen.(2)Uniaxial compression test: Displacement control (at a rate of 0.1 mm/s) is used to apply axial pressure to the specimen.(3)Triaxial compression test: (1) For the fine-sandstone sample, axial pressure and confining pressure are gradually applied to the hydrostatic pressure σ1 = σ2 (σ3) = 5 MPa, and the constant confining pressure remains unchanged, using displacement control (at a rate of 0.1 mm/s) to apply an axial pressure until the sample is destroyed. At the end of the test, the rock sample is replaced, and the confining pressure is changed to 5 MPa, 10 MPa, 15 MPa, 20 MPa, and 25 MPa. (2) For the remoulded sample of silty mudstone and sand-mudstone interlayer, the axial pressure and confining pressure are gradually applied to the hydrostatic pressure σ1 = σ2 (σ3) = 2 MPa, and the constant confining pressure remains unchanged. Displacement control (at a rate of 0.1 mm/s) is used to apply the axial pressure until sample failure, the rock sample is replaced, and the confining pressure is changed to 2 MPa, 3 MPa, 4 MPa, 5 MPa, and 6 MPa, respectively.

3.3. Test Equipment

The test of the mechanical parameters of the sample adopts the RMT-150B electrohydraulic servo test system developed by the Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, as shown in Figure 3. The test system has a maximum axial load of 1000 kN, a maximum horizontal load of 500 kN, and a maximum confining pressure of 50 MPa. It can perform rock tests such as uniaxial compression, indirect (direct) tension, compression shear, and triaxial compression. It can adopt various control modes of load, displacement, and stroke. During the test, a computer automatically collects the load and deformation data and displays them in real time.

3.4. Analysis of Rock Sample Results
3.4.1. Analysis of Brazilian Split Test Results

The basic principle of Brazilian splitting is based on the elastic theoretical solution of a disk subjected to diametral compression. The maximum tensile stress acting on the centre of the sample when the sample is damaged iswhere σt is the maximum tensile stress in the centre of the sample, which is the tensile strength, Pa; is the ultimate pressure when the sample is damaged, N; and D and h are the diameter and thickness of the pressure disc, respectively, mm.

According to the basic parameters and test results of the sample, the tensile strength of the sample can be calculated from formula (1), as shown in Table 1. The average tensile strength of the silty mudstone is approximately 1.44 MPa, the average tensile strength of the sandstone mudstone interlayer is approximately 1.61 MPa, and the average tensile strength of the fine sandstone is approximately 3.70 MPa.

3.4.2. Analysis of Uniaxial Compression Test Results

The compressive strength of each sample is obtained from the complete stress-strain curve of each sample after uniaxial compression, and the elastic modulus and Poisson’s ratio of each sample are calculated, as shown in Table 2. According to Table 2, the average uniaxial compressive strength of a silty-mudstone remoulded sample is 13.86 GPa, the average elastic modulus is 1.48 GPa, and the average Poisson’s ratio is 0.14. The average uniaxial compressive strength of the sand-mudstone interlayer remoulded sample is 12.28 MPa, the average elastic modulus is 1.54 GPa, and the average Poisson’s ratio is 0.09. The average uniaxial compressive strength of a fine-sandstone sample is 74.20 MPa, the average elastic modulus is 6.74 GPa, and the average Poisson’s ratio is 0.23.

According to the mass, diameter, and height of each sample (Table 2), it can be calculated that the density of a silty-mudstone sample is 2190 kg/m3, the density of a sand-mudstone interlayer sample is 2197 kg/m3, and the density of a fine-sandstone sample is 2486 kg/m3.

3.4.3. Analysis of Triaxial Compression Results

According to the complete stress-strain curve of each sample after triaxial compression, the compressive strength of each sample under different confining pressures is obtained, as shown in Tables 3 and 4.

In the field of rock mass engineering, the pseudotriaxial compression failure of rock conforms to the Mohr-Coulomb strength criterion, as shown in Figure 4(a). The Mohr-Coulomb strength criterion is widely used for rock under the action of compressive stress. The criterion considers that failure occurs when the shear stress τ at a point in the rock mass reaches the limit stress τs, and the expression is shown in formula:where σ is the normal stress, c is the cohesion, and φ is the internal friction angle.

The maximum principal stress σs and the minimum principal stress σc have a linear relationship [20], as shown in Figure 4(b), and the expression is shown as follows:where σc is the uniaxial compressive strength, MPa; k is the slope of the strength envelope, ; φ is the internal friction angle.

According to formulas (2) and (3), Mohr’s circle and envelope of the silty-mudstone remoulded samples, sand-mudstone interlayer remoulded samples, and fine-sandstone samples are plotted, as shown in Figure 5, and then the internal friction angle and cohesion value of the three samples are calculated, as shown in Tables 3 and 4.

Through the observation of the rock mass characteristics of the strata that the roadway passes through during the development process, the GSI (Geological Strength Index) engineering rock mass classification is used to evaluate the rock mass via the quantitative value of GSI [21], as shown in Table 5.

Then classify the surrounding rock masses of the south wing track uphill, so as to divide the surrounding rock types of the south wing centralized track transportation lane into three categories: silty mudstone (category V, integrity coefficient 0.15), sand-mudstone interlayer (category IV, integrity coefficient 0.35), and fine sandstone (category III, integrity coefficient 0.55).

Due to the development of cracks in the field, the mechanical parameters measured by the samples prepared in the laboratory cannot directly reflect the physical and mechanical properties of the rock mass. Therefore, in this paper, the test results of laboratory measurements are reduced based on the integrity coefficient of the rock mass type on site. The mechanical parameters of the rock mass after reduction are shown in Table 6.

4. Simulation Analysis of Surrounding Rock Stability of Roadway

4.1. Scheme Design

According to the engineering background, the cross-sectional shape of the roadway is a semicircular arch with a straight wall, the net cross-sectional size is width × height = 3.72 m × 3.42 m, and the coordinate axis is located at the centre of the model. In order to analyze the distribution law of surrounding rock stress, deformation, and plastic zone after roadway excavation under different lithologic conditions, two schemes were designed for simulation.(1)Under the condition of a single-rock mass (silty mudstone, sand-mudstone interlayer, or fine sandstone), a total of three models are established. According to engineering geological conditions, the model size is X × Y × Z = 60 m × 11 m × 60 m under the condition of a silty-mudstone rock mass, and the model size is X × Y × Z = 60 m × 12 m × 60 m under the condition of a sand-mudstone interlayer rock mass, and the model size is X × Y × Z = 60 m × 14 m × 60 m under the condition of a fine-sandstone rock mass. The model is shown in Figure 6(a).(2)Under the condition that the roadway passes through different rock layers (silty mudstone, sand-mudstone interlayer, and fine sandstone), the model size is X × Y × Z = 60 m × 37 m × 60 m, and the model is shown in Figure 6(b).

4.2. Boundary Conditions

FLAC3D5.0 [22] numerical simulation software was used for simulation analysis, the bottom of the model is fixed, the left and right sides of the model are restrained by displacement, the front and rear of the model are restrained by displacement, and the top of the model is subjected to the overburden load. The burial depth of the silty mudstone is 380 m, the burial depth of the sand-mudstone interlayer is 394.2 m, and the burial depth of the fine sandstone is 405 m. Assuming that the weight of the rock mass is 24 kN/m2, it can be calculated that the applied load on top of the silty-mudstone model under a single-rock mass is 9.12 MPa, the applied load on top of the sand-mudstone interlayer model is 9.46 MPa, and the applied load on top of the fine-sandstone model is 9.72 MPa.

4.3. Analysis of the Simulation Results for a Single-Rock Mass Type

Two monitoring lines are set on the top and bottom plates and the two sides of the model, and the calculation results are imported into “Tecplot” software for processing. A schematic diagram of the monitoring line layout is shown in Figure 7.

4.3.1. Stress Analysis

The variation laws of the surrounding rock stress along the vertical and horizontal survey lines after tunnel construction under different lithology conditions are shown in Figure 8.

It can be seen that, after the tunnel construction, the vertical stress exhibits stress concentration at the two sides of the tunnel, and the horizontal stress exhibits stress concentration in the roof and floor of the tunnel. When the lithology is silty mudstone, the vertical stress concentration is approximately 14.3 MPa at a location 16.01 m from the centre of the roadway. The horizontal stress concentration is approximately 11.64 MPa at a location 14.26 m from the roadway roof toward the roadway centre and approximately 11.08 MPa at a location 13.65 m from the roadway floor toward the roadway centre. When the lithology is a sand-mudstone interlayer, the vertical stress concentration is approximately 14.65 MPa at a location 11.21 m from the centre of the roadway. The horizontal stress concentration is approximately 12.46 MPa at a location 9.98 m from the roadway roof toward the roadway centre and approximately 12.76 MPa at a location 10.67 m from the roadway floor toward the roadway centre. When the lithology is fine sandstone, the vertical stress concentration is approximately 14.57 MPa at a location 7.51 m from the centre of the roadway. The horizontal stress concentration is approximately 13.69 MPa at a location 7.61 m from the roadway roof toward the roadway centre and approximately 13.54 MPa at a location 7.61 m from the roadway floor toward the roadway centre. It can be seen from the analysis that the horizontal stress on the vertical line and the vertical stress concentration on the horizontal line transfer to the depth of the surrounding rock and gradually weaken with the decrease in the lithologic strength.

4.3.2. Displacement Analysis

The variation laws of surrounding rock displacement along the horizontal and vertical survey lines after tunnel construction under different lithology conditions are shown in Figure 9. After roadway construction, roof subsidence, floor heave, and two sides’ shrinkage, the closer the roadway is to the centre of the roadway, the larger the surrounding rock deformation is. When the lithology is silty mudstone, the roof-to-floor convergence of the roadway is 1110.69 mm, and the convergence of the two sides is 1121.49 mm. When the lithology is sand-mudstone interlayer, the roof-to-floor convergence of the roadway is 757.28 mm, and the convergence of the two sides is 689.53 mm. When the lithology is fine sandstone, the roof-to-floor convergence of the roadway is 348.25 mm, and the convergence of the two sides is 343.75 mm. It can be seen from the above analysis that, with the decrease of rock mass strength, the roof-to-floor convergence and the two sides’ convergence gradually increase, and the farther away from the roadway centre, the smaller the deformation.

4.3.3. Plastic Zone Analysis

After tunnel construction, the surrounding rock exhibits tensile failure and shear failure. The distribution laws of the surrounding plastic area after tunnel construction under different lithology conditions are shown in Figure 10. The plastic zone area gradually decreases with increasing lithologic strength.

4.4. Analysis of Multilayer Simulation Results
4.4.1. Displacement Analysis

Figure 11(a) shows the movement law of roof strata under the condition of passing through multiple strata during tunnel excavation. The roof rock layer deformation is approximately 109.95 mm at Y = 6.31 m when the roadway is driven for 3 m, and the roof rock layer deformation is approximately 238.73 mm at Y = 7.13 m when the roadway is driven for 6 m. When the roadway is driven for 9 m, 12 m, 15 m, 18 m, and 21 m, the deformation of the roof strata reaches the maximum at Y = 9.75 m, corresponding to deformations of 338.19 mm, 423.78 mm, 484.31 mm, 503.34 mm, and 538.98 mm. When the roadway is driven for 24 m and 27 m, the deformation of roof strata reaches a maximum at Y = 15.73 m, corresponding to deformations of 547.45 mm and 567.90 mm, respectively. For the model, in the axial direction (Y direction), the layer in the range of 0 to 11 m is the silty mudstone, the layer in the range of 11 to 23 m is the sand-mudstone interlayer, and the layer in the range of 23 to 37 m is the fine sandstone. As a result, the roof rock layer fluctuates when the roadway passes through different lithologies, and the roof rock layer at the interface of the silt-mudstone and sand-mudstone interlayer rock layers decreases first and then increases.

4.4.2. Stress Analysis

Figure 11(b) shows the evolution law of the front abutment stress under the condition of crossing multiple rock layers during the tunneling process. The support stress appears in the front and back of the roadway after driving, and the abutment stress moves forward with increasing driving size, forming the movable abutment stress. When the roadway is driven for 3 m, the front abutment stress reaches a maximum of 11.03 MPa at Y = 12.21 m; when the roadway is driven for 6 m, the front abutment stress reaches a maximum of 11.65 MPa at Y = 14.24 m; when the roadway is driven for 9 m, the front abutment stress reaches a maximum of 12.01 MPa at Y = 17.23 m; when the roadway is driven for 12 m, the front abutment stress reaches a maximum of 12.27 MPa at Y = 19.90 m; when the roadway is driven for 15 m, the front abutment stress reaches a maximum of 12.72 MPa at Y = 23.19 m; when the roadway is driven for 18 m, the front abutment stress reaches a maximum of 12.85 MPa at Y = 26.25 m; when the roadway is driven for 21 m, the front abutment stress reaches a maximum of 12.84 MPa at Y = 28.88 m; when the roadway is driven for 24 m, the front abutment stress reaches a maximum of 12.95 MPa at Y = 31.90 m; when the roadway is driven for 27 m, the front abutment stress reaches a maximum of 13.28 MPa at Y = 34.90 m. These results are shown in Figure 11(b).

4.4.3. Plastic Zone Analysis

The distribution laws of the plastic zone around the surrounding rock under different sizes of roadway driving are shown in Figure 12. After tunnel construction, the surrounding rock exhibits shear and tensile failure. With increasing driving size, the scope of the plastic zone around the tunnel gradually increases. However, due to the different lithologies, the range of the plastic zone is different in different lithology regions.

In order to more vividly show the failure characteristics of surrounding rock around the roadway, write fish statement to extract the number of unit failure of surrounding rock around the roadway, and draw as shown in Figure 13. Shear and tensile failure occur in the surrounding rock after tunnel excavation, and the number of shear-now units and shear-past units is far greater than that of tension-past units, but there are no tension-now units. With the increase in tunnel driving size, the number of shear-now and shear-past elements increases linearly, while the number of tension-past elements is small and first increases and then decreases slowly.

5. Instability Mechanism of Surrounding Rock and Surrounding Rock Control Technology and Application in a Fracture Zone

5.1. Deformation and Failure Mechanism

From the deformation and failure characteristics of the roadway, it can be seen that the existing support form of the Xinyi Coal Mine has difficulty meeting the functional requirements of the roadway and that the support means adopted cannot effectively control the continuous deformation of the surrounding rock of the roadway. The mechanism of roadway instability is as follows:(1)Fractures develop in the surrounding rock. The surrounding rocks in the tectonic area are subject to tension and compression due to the fault activity, cracks develop, the surrounding rock becomes broken, and the self-stabilizing ability is poor.(2)Surrounding rock has poor lithologic strength and undergoes cementation. The fault zone is mainly composed of fault mud and argillaceous rocks. These rocks are greatly affected by water: when in contact with water, they expand and swell, have strong softening properties, sharply decrease in strength, and lose bearing capacity.(3)Gush of water. The sandstone water at the top and bottom of the Xinyi Coal Mine is a weak aquifer. The fissure water is controlled by the development degree of fissures and structures, which clearly varies among different sections. The fissure water is static reserve water, but the water pouring into the roadway is closely followed by changes in the hydraulic head, which cause certain inconveniences during the construction.(4)The strength of the original support system is low. The original support mostly used an anchor rod with a length of 1.8 m, and the pretightening force could not be applied in time, resulting in premature separation and deformation of the surrounding rock.(5)Rheological changes of the rock surrounding the roadway. The initial support form of the surrounding rock of the roadway is anchor shotcrete support, but, due to untimely spraying, weathering and even loosening of the surrounding rock may easily cause failure of the anchor rod and make the support structure unstable. Under the action of high stress and fault tectonic stress, the surrounding rock of the roadway undergoes rheological changes.

5.2. Control Technology and Parameters

Based on the above analysis, the form of closed support + shotcrete + grouting + anchor mesh cable coupling support is proposed. Steel support can prevent the collapse of broken surrounding rock, shotcrete can seal the surrounding rock and prevent the weathering of the surrounding rock surface, and grouting can improve the self-bearing capacity of the surrounding rock and enhance the anchoring effect of the anchor bolt; a bottom arch beam can control the floor heave; a steel support and an anchor cable can be coupled through a structural compensation anchor cable to control the deformation of the surrounding rock and fully utilize the advantages of active and passive support. The construction process is as follows: driving section ⟶ temporary support ⟶ installation of anchor bolt ⟶ initial shotcreting 30 mm ⟶ installation of U-shaped steel support ⟶ installation of anchor cable ⟶ shotcreting to a given thickness of 150 mm ⟶ installation of grouting anchor bolt ⟶ grouting. The support design drawing is shown in Figure 14.(1)Anchor rod parameters. A high-strength left-handed nonsteel rib steel anchor with a diameter of 22 mm and length of 2400 mm, two Z2350 resin cartridges with an anchor length of 1200 mm, row spacing between anchors of 700 × 700 mm, and anchor pretightening force of at least 150 kN was adopted. The torque force applied by the anchor nut is at least 132 Nm, the anchor is perpendicular to the wall of the roadway, the foot is installed 15° to the wall of the roadway, the yield strength is 400 MPa, and the tensile strength is 500 MPa.(2)Anchor cable parameters. Seven strands of high-strength relaxation steel wire anchor cable with diameter of 17.8 mm and length of 6500 mm are used, and four coils of Z2350 resin cartridge are used for anchoring. The anchorage length is 2000 mm, the row spacing between anchors is 1400 × 1400 mm, and the anchor pretightening force is not less than 200 kN.(3)Shotcrete parameters. The strength is not less than C25, cement : sand : gravel : water = 1 : 1.94 : 2.79 : 0.49, medium coarse sand, gravel diameter: 5∼7 mm, accelerator model is J85, the mixing amount is generally 2∼4% of the cement weight, the upper limit of shotcrete arch is taken, the accelerator must be evenly added at the feeding port of the shotcrete machine, and the total thickness of each section of the spraying layer is 150 mm.(4)Grouting parameters. The grouting material is cement-water glass single-liquid slurry using slag Portland cement, and the water : cement ratio is 0.75 : 1.525. Using a grouting tube with a diameter of 22 mm and a length of 2500 mm, the grouting volume of a single hole is 1∼1.5 m³, the grouting pressure is 0.1∼1.5 MPa, the grouting flow is 3.0∼3.5 m³/h, and the spacing between the grouting holes is 1600 mm × 1600 mm.(5)U-shaped steel closed bracket. U36 steel: the row spacing of the bracket is 1400 mm, and the thickness of the spray gun is 150 mm.

5.3. Deformation Monitoring

After adopting new support measures, a displacement observation station was set up on the south wing concentrated track, and a total of three roadway surface surrounding rock stations were arranged at a 10 m spacing along the fault fracture zone. The homemade observation stand and laser rangefinder were used for observation, and the curve of roadway deformation with time was drawn, as shown in Figure 15.

Figure 15(a) shows that the roof-to-floor convergence of the roadway is 35 mm, 38 mm, and 25 mm within 100 days of observation. From Figure 15(b), the convergence of the two sides of the roadway is 45 mm, 37 mm, and 56 mm within 100 days of observation. The overall reinforcement effect of the roadway is good, and the roadway after the new support measures is shown in Figure 16. The surface of the roadway is smooth, and there is no phenomenon of concrete cracking or anchor fracture.

6. Conclusion

(1)The rock blocks were collected on site at the fracture zone, and remoulded samples were prepared for mechanical experiments in the laboratory. The basic mechanical parameters of the roadway passing through silty mudstone, sand-mudstone interlayer, and fine sandstone were analyzed.(2)A three-dimensional model was established to analyze the distribution of stress, deformation, and plastic area in the surrounding rock mass after the tunnel passes through, considering both a single-rock mass and a multilayer-rock mass.(3)We proposed the “closed support + shotcrete + grouting + anchor mesh cable coupling support form” and arranged the observation station in the field for deformation monitoring. It is found that the deformation of the roof, floor, and two sides of the roadway is small, the roadway surface is smooth, and the overall reinforcement effect is good.

Data Availability

The data used to support the finding of this study have not been made available because research projects is in pregress.

Conflicts of Interest

The authors declare no conflicts of interest.

Acknowledgments

This work was supported by the Research Fund of State and Local Joint Engineering Laboratory for Gas Drainage & Ground Control of Deep Mines (Henan Polytechnic University) (no. SJF202004), Doctoral Research Initiation Fund of Huaiyin Institute of Technology (no. Z301B20536), Jiangsu Provincial Department of Housing and Urban Rural Development Project (no. Z413B19341), and the National Natural Science Foundation of China (no. 51974104).