Study and Application of Rock Breaking Mechanism of Concentrated Water Hydraulic Smooth Blasting in Broken Sand-Stone Geological Conditions

Table 6

Detailed hole layout parameters.

Gun hole nameDetonator section timesNumber of gun holesHole deep (m)Row spacing (cm)Hole spacing (cm)Angle (°)Charging factorSingle hole loading capacity (kg)

Bottom trenching141.9242580450.561.5
383.758540520.643
543.774580620.602.4
743.790580780.471.8

Upper trenching141.9242580450.561.5
363.758550520.643
543.774580620.603
743.790580780.471.8

Auxiliary hole733.780100900.572.1
933.760130900.491.8
1173.760120900.491.8
13173.75090900.411.5

Peripheral holes15373.76070880.841.2
Base plate hole17113.785130900.491.8