Research Article

An Adaptive Framework for Selecting Environmental Monitoring Protocols to Support Ocean Renewable Energy Development

Table 9

Component decision tree for impacts on benthic habitat and resources. The key is followed to obtain a recommended suite of monitoring protocols.

Determine which impacts to the benthic environment need to be monitored:

The energy resource is
WindGo to A
WavesGo to B
TidalGo to C
(A) The wind turbine foundation is
Monopile OR tripod OR latticeGo to A1
GravityGo to A2
Floating mooringGo to A3
 (A1) The stage of the monopile, tripod, or lattice wind turbine project is
 ConstructionZ1, Z2
 OperationZ1, Z2, Z3
 DecommissioningZ1, Z2
 (A2) The stage of the gravity wind turbine project is
 ConstructionZ1, Z2, Z3
 OperationZ1, Z2, Z3
 DecommissioningZ1, Z2, Z3
 (A3) The stage of the floating mooring wind project is
 ConstructionZ1, Z2
 OperationZ1, Z2
 DecommissioningZ1, Z2
(B) The tidal turbine type is
Open OR shrouded bottom mountedGo to B1
Open OR shrouded floating mooringGo to B2
 (B1) The stage of the bottom-mounted tidal turbine project is
 ConstructionZ1, Z2
 OperationZ1, Z2, Z3, Z4
 DecommissioningZ1, Z2
 (B2) The stage of the floating mooring tidal turbine project is
 ConstructionZ1, Z2
 OperationZ1, Z2, Z4
 DecommissioningZ1, Z2
(C) The wave device type is
Point absorber OR wave attenuator OR oscillating water columnGo to C1
Oscillating wave surge converterGo to C2
OvertoppingGo to C3
 (C1) The stage of the point absorber OR wave attenuator OR oscillating water column project is
 ConstructionZ1, Z2
 OperationZ2, Z4
 DecommissioningZ1, Z2
 (C2) The oscillating wave surge converter project scale is
 ConstructionZ1, Z2
 OperationZ1, Z2, Z3, Z4
 Decommissioning Z1, Z2
 (C3) The overtopping device project scale is
 ConstructionZ1, Z2
 OperationZ1, Z2, Z4
 DecommissioningZ1, Z2

Recommended protocols:
Z1: seabed scour and/or deposition.
Z2: changes in benthic community composition.
Z3: increase in hard bottom habitat.
Z4: changes in hydrodynamics.