SEM-PLS Analysis of Inhibiting Factors of Cost Performance for Large Construction Projects in Malaysia: Perspective of Clients and Consultants
Table 2
Results of measurement model evaluation.
| | First iteration | Final iteration | | Loading | AVE | CR | Alpha | Loading | AVE | CR | Alpha |
| CSM01 | 0.639 | 0.462 | 0.870 | 0.879 | 0.635 | 0.537 | 0.872 | 0.835 | CSM02 | 0.560 | | | | Omitted | | | | CSM03 | 0.515 | | | | Omitted | | | | CSM04 | 0.844 | | | | 0.844 | | | | CSM05 | 0.815 | | | | 0.826 | | | | CSM06 | 0.641 | | | | 0.651 | | | | CSM07 | 0.758 | | | | 0.769 | | | | CSM08 | 0.585 | | | | 0.637 | | | | DDF01 | 0.772 | 0.467 | 0.795 | 0.874 | 0.806 | 0.640 | 0.873 | 0.852 | DDF02 | 0.401 | | | | 0.553 | | | | DDF03 | 0.873 | | | | 0.921 | | | | DDF04 | 0.331 | | | | Omitted | | | | DDF05 | 0.839 | | | | 0.870 | | | | FIN01 | 0.596 | 0.459 | 0.832 | 0.815 | 0.571 | 0.533 | 0.816 | 0.754 | FIN02 | 0.624 | | | | 0.633 | | | | FIN03 | 0.604 | | | | Omitted | | | | FIN04 | 0.518 | | | | Omitted | | | | FIN05 | 0.813 | | | | 0.807 | | | | FIN06 | 0.846 | | | | 0.867 | | | | ICT01 | 0.867 | 0.786 | 0.917 | 0.880 | 0.867 | 0.786 | 0.917 | 0.880 | ICT02 | 0.912 | | | | 0.912 | | | | ICT03 | 0.881 | | | | 0.881 | | | | LAB01 | 0.861 | 0.577 | 0.871 | 0.828 | 0.861 | 0.577 | 0.871 | 0.828 | LAB02 | 0.793 | | | | 0.793 | | | | LAB03 | 0.778 | | | | 0.778 | | | | LAB04 | 0.726 | | | | 0.726 | | | | LAB05 | 0.617 | | | | 0.617 | | | | MMF01 | 0.795 | 0.625 | 0.866 | 0.821 | 0.795 | 0.625 | 0.866 | 0.821 | MMF02 | 0.909 | | | | 0.909 | | | | MMF03 | 0.575 | | | | 0.575 | | | | MMF04 | 0.842 | | | | 0.842 | | | | PMCA01 | 0.539 | 0.444 | 0.757 | 0.702 | Omitted | 0.515 | 0.757 | 0.737 | PMCA02 | 0.626 | | | | 0.590 | | | | PMCA03 | 0.812 | | | | 0.848 | | | | PMCA04 | 0.658 | | | | 0.692 | | | |
|
|