SEM-PLS Analysis of Inhibiting Factors of Cost Performance for Large Construction Projects in Malaysia: Perspective of Clients and Consultants
Table 4
Path coefficient with
-values for the structural model.
| | | Path coefficient () | -value |
| CSM | Contractor’s Site Management Related Factors | −0.718 | 49.43* | DDF | Design and Documentation Related Factors | 0.194 | 11.59* | FIN | Financial Management Related Factors | 0.193 | 14.80* | ICT | Information and Communication Related Factors | 0.145 | 9.43* | LAB | Human Resource (Workforce) Related Factors | 0.298 | 21.82* | MMFM | Nonhuman Resource Related Factors | 0.043 | 4.01* | PMCA | Project Management and Contract Administration Related Factors | 0.102 | 3.55* |
|
|
.
|