Heuristics for Multiobjective Optimization of Two-Sided Assembly Line Systems

Table 4

Allocation of tasks for 2nd assignment of P19 (CT = 6 min).

W/S typeAllotted tasksProcessing time for task “ Work load at each stationIdle time at each station

W/S(L)-11
3
2.80
2.50
5.300.70
W/S(R)-123.103.102.90
W/S(L)-2
W/S(R)-243.403.402.60
W/S(L)-38
7
3.30
2.60
5.900.10
W/S(R)-362.702.703.30
W/S(L)-4114.104.101.90
W/S(R)-410
13
3.70
1.80
5.500.50
W/S(L)-553.203.202.80
W/S(R)-5141.201.204.80
W/S(L)-695.905.900.10
W/S(R)-6175.805.800.20
W/S(L)-712
16
2.20
2.40
4.601.40
W/S(R)-7
W/S(L)-8152.302.303.70
W/S(R)-8
W/S(L)-918
19
3.80
2.10
5.900.10
W/S(R)-9