An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation

Table 1

Construction activities with resource and work options.

Activity groupActivity
ID
Quantity ( )Productivity (LPRDmin–LPRDmax)Overtime factor ( )LaborMaterialEquipmentAdministration
Cost rate ( ) ($/d)Labor cost ( )Labor quality (LQmin–LQmax)Cost (MCmin–MCmax) ($)Quality (MQmin–MQmax)Cost (ECmin–ECmax) ($)Quality (EQmin–EQmax)Productivity factor (DEKmin–DEKmax)Cost rate (ACRmin–ACRmax) ($/d)Quality (AQmin–AQmax)Cost ( ) ($)

Earth work1240 m3100–150 m3/d1–1.57000.8–1.03200–45000.7–1.0600–6500.8–1.00.8–1.290–1500.7–1.0

Foundation 2110 m210–12 m2/d1–1.53000.8–1.0800–11000.7–1.0110–1200.8–1.00.98–1.0290–1500.7–1.0
31.6 t0.6–0.8 t/d1–1.56000.7–1.05600–72000.7–1.0128–1440.8–1.00.9–1.190–1500.7–1.0
452 m315–20 m3/d1–1.57500.9–1.018200–234000.7–1.0150–1800.9–1.00.95–1.0590–1500.7–1.0
575 m38–12 m3/d1–1.517000.8–1.016000–200000.7–1.01500–18000.8–1.00.98–1.0290–1500.7–1.0
660 m320–25 m3/d1–1.54300.8–1.06400–86000.7–1.0120–1500.8–1.00.9–1.190–1500.7–1.0

1st story7120 m28–11 m2/d1–1.54500.7–1.01200–17000.7–1.0210–2300.9–1.00.98–1.0290–1500.7–1.0
83.2 t0.8–1.2 t/d1–1.58000.7–1.011200–144000.7–1.0256–2880.8–1.00.9–1.190–1500.7–1.0
948 m37–10 m3/d1–1.510000.7–1.016800–216000.7–1.0200–2400.9–1.00.95–1.0590–1500.7–1.0
1062 m34–6 m3/d1–1.57500.8–1.013200–166000.7–1.01240–14880.8–1.00.98–1.0290–1500.7–1.0

2nd story11105 m28–11 m2/d1–1.54600.7–1.01100–16000.7–1.0180–2000.8–1.00.98–1.0290–1500.7–1.0
122.8 t0.8–1.2 m2/d1–1.58000.7–1.09800–126000.7–1.0224–2520.8–1.00.9–1.190–1500.7–1.0
1343 m37–10 m3/d1–1.510000.7–1.015050–193500.7–1.0180–2100.9–1.00.95–1.0590–1500.7–1.0
1455 m34–6 m3/d1–1.57500.8–1.011700–147000.7–1.01100–13200.8–1.00.95–1.0590–1500.7–1.0

3rd story1595 m27–10 m2/d1–1.54700.7–1.01100–16000.7–1.0180–2100.8–1.00.95–1.0590–1500.7–1.0
162.2 t0.8–1.2 t/d1–1.58000.7–1.07700–99000.7–1.0176–1980.8–1.00.9–1.190–1500.7–1.0
1738 m37–10 m3/d1–1.510000.7–1.013300–171000.7–1.0175–1900.9–1.00.95–1.0590–1500.7–1.0
1850 m34–6 m3/d1–1.57500.8–1.010600–133000.7–1.01000–12000.8–1.00.9–1.190–1500.7–1.0

Roof19135 m218–24 m2/d1–1.53000.7–1.03200–38000.7–1.040–500.8–1.00.98–1.0290–1500.7–1.0
20160 m240–50 m2/d1–1.57500.7–1.07000–85000.7–1.0100–1200.8–1.00.98–1.0290–1500.7–1.0