An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation

Table 2

The quality weight indicators.

Group worksQuality weight indicators of group works ( )Activity (i)
(ID)
Quality weights indicators of activity (i)
( )
Quality weight indicators of labors (i)
( )
Quality weight indicators of materials (i)
( )
Quality weight indicators of equipment (i)
( )
Quality weight indicators of administration (i)
( )

Earth work0.0510.050.10.70.150.05

Foundation work 0.2520.050.10.70.150.05
30.060.10.70.150.05
40.060.10.70.150.05
50.060.10.70.150.05
60.020.10.70.150.05

1st story work 0.270.050.10.70.150.05
80.050.10.70.150.05
90.050.10.70.150.05
100.050.10.70.150.05

2nd story work 0.2110.050.10.70.150.05
120.050.10.70.150.05
130.050.10.70.150.05
140.050.10.70.150.05

3rd story work 0.15150.030.10.70.150.05
160.040.10.70.150.05
170.040.10.70.150.05
180.040.10.70.150.05

Roof work 0.15190.070.10.70.150.05
200.080.10.70.150.05

1.01.0