The Feasibility of a Land Ferry System to Reduce Highway Maintenance Cost and Associated Externalities

Table 1

Results of the economic impact analysis.

ItemInitial investment/final demand change⁢Total⁢Nevada
OutputEarningsJobsOutputEarningsJobs

Phase one: construction
1Track1,902,389,0003,461,113,307965,644,35122,6042,990,729,331860,582,48919,912
2Stations71,204,000135,692,39045,746,8491,061119,325,89840,328,442932
3Support347,240,000677,986,100226,469,9285,183673,885,850225,100,3085,152
4Land696,050,0001,300,811,425416,870,41010,8001,297,056,768415,616,22910,771
5Communications79,150,000145,013,29039,807,9301,07495,685,62925,564,444664
6Vehicles15,000,00024,108,3005,489,60014116,839,2583,838,17699
7Professional services704,981,0001,303,199,892457,660,16711,847908,719,582318,602,0528,258

Totals$3,816,014,0007,047,924,7042,157,689,23552,709$6,102,242,316$1,889,632,14045,788

Proportion of total benefitting Nevada86.58%87.58%86.87%

Phase two: operations
1Utilities8,657,00015,984,2855,479,01514815,984,2855,479,015148
2Fuel6,727,00011,662,6002,741,9255811,662,6002,741,92558
3Operator328,000593,713141,7293178,11442,5191
4Administrative maintenance1,443,0002,607,645865,511392,607,645865,51139
5Track maintenance26,304,00047,612,87011,365,95822414,283,8613,409,78867
6Engine maintenance750,0001,357,575324,0756923,151220,3714

Totals44,209,00079,818,68820,918,213478$45,639,656$12,759,128318

Proportion of total benefitting Nevada57.18%61.00%66.41%

For 40 years$1,825,586,234$510,365,134318