Research Article

Cost Estimation Model Using Modified Parameters for Construction Projects

Table 1

Item simplification.

StepContentsMethodNo. of itemsSpecifications

1Investigating the no. of itemsAnalyzing bill of quantities24
2Grouping itemsConcrete, forms, steel bar, and other24No. of items: concrete (5), forms (6), steel bars (7), and other (3)
3Selecting a unit cost applicationConcrete, forms, and steel bar: quantity based; other: cost based21Cost ratio: concrete 24.88%, forms 49.73%, steel bar 25.17%, and other 0.22%
4Item simplificationIntegrating items which have similar unit costs15Ratio of unit cost error: 180 concrete (2): 1.42%, steel bar (6): 1.56%
5Exception of items estimated by automationConcrete pouring and steel cutting12Concrete pouring = concrete × 1.01
Steel cutting = steel bar/1.03