Research Article
Cost Estimation Model Using Modified Parameters for Construction Projects
| Step | Contents | Method | No. of items | Specifications |
| 1 | Investigating the no. of items | Analyzing bill of quantities | 24 | — | 2 | Grouping items | Concrete, forms, steel bar, and other | 24 | No. of items: concrete (5), forms (6), steel bars (7), and other (3) | 3 | Selecting a unit cost application | Concrete, forms, and steel bar: quantity based; other: cost based | 21 | Cost ratio: concrete 24.88%, forms 49.73%, steel bar 25.17%, and other 0.22% | 4 | Item simplification | Integrating items which have similar unit costs | 15 | Ratio of unit cost error: 180 concrete (2): 1.42%, steel bar (6): 1.56% | 5 | Exception of items estimated by automation | Concrete pouring and steel cutting | 12 | Concrete pouring = concrete × 1.01 Steel cutting = steel bar/1.03 |
|
|